South Street Building Expansion Project

Mendocino Coast Clinics' Ground Broken!

 Congressman Mike Thompson Wields Golden Shovel

 Swithenbank Construction of Fort Bragg, has completed our facility expansion! The Grand Opening of the Liz Irwin wing will be March 23, 2013!

Mendocino Coast Clinics has won a $2,580,000 grant from the Capital Development program of the Affordable Care Act (ACA), the legislation to expand health care coverage for all Americans to be fully implemented in 2014.

  • MCC was one of 18 community health centers in California to receive this award.
  • MCC will expand its South Street facility, which opened in 2003.  
  • MCC will build 6920 SF addition providing more:
    • Behavioral Medicine & Counseling Rooms
    • Dental Operatories 
    • Administrative Offices 
    • Kitchen suitable for disaster use 
    • Community Conference Room

Project timelines:

  • September -November 2011   Done!
    • Complete architectural designs, project manual and specifications
    • Complete Request For Qualifications process for potential contractors
  • January -February 2012   Done!
    • Complete Request for Proposal process
  • March 2012   Done!
    • Choose building contractor
  • April 2012   Done!  
    • Construction has begun!
  • November 2012 ~ Building Completed!

The South Street Building Expansion Project will allow MCC to provide more efficient and effective services to more patients as well as bolstering the local economy.

 

Click on an image to view the image gallery.


 